07-02-2013 5:48 PM
Current STO's to Singapore (for example) are arriving past the need date. No route is being used, material is in stock. Delivery date proposed 139 days after create Date
STO Create Date: 6/18/2013
Delivery Date: 11/4/2013
PDT varies
GR Proc Time - 0 to 49 d
Pick / Pack Time: 2 d
Staging Time = 0
Loading Time = 0
TP Time = 0
GI Time = 0
Delivery Creation Date varies
We know our average Ocean transport time is 56 days. What is the most efficient method to add the transport time?
07-23-2013 4:42 PM
Hi Griff,
As per my understanding, the Delivery date includes the average ocean transport time of 56 days.
for all the time frames which you want to include in your delivery document, you can create each as an event and record the planned and actual time period against each event. the events can be created at inbound delivery document creation (VL31N), at header level in dates tab.
please refer below screen shot and explore this possibility.
Regards,