Hi experts,
I have a scenario where the company just procures an assembly A,which consists of Items(sub assemblies) B and C,Also B will have 9 components and C will have 20 components.I have to run MRP for item A and i should get the pr proposal for all items & components(B&C and down the level items) in one PR.The components are procured from out side.No sales order,no demand management.Is this possible?
Thimmayya
Hi Thimmayya,
All material type will be ROH. Create BOM for material A with B, C and all required components. Make BOM single level for material A. Set reorder point to material A. Run MRP MD02. It will give you planned order for A. Go to display planned order all components will be there for the planned order. Now convert planned order to Pur. req -- Pur. Order- all components will be there for the pur. order A.
I think this will solve your problem. Revert back if you have any issue.
Thanks,
Biplob
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.