Hi experts,

I have a scenario where the company just procures an assembly A,which consists of Items(sub assemblies) B and C,Also B will have 9 components and C will have 20  components.I have to run MRP for item A and i should get the pr proposal for all items & components(B&C and down the level items) in one PR.The components are  procured from out side.No sales order,no demand management.Is this possible?

Thimmayya

Accepted Solutions (1)

Accepted Solutions (1)

biplob_chowdhury15
Active Participant
0 Kudos

Hi Thimmayya,

All material type will be ROH. Create BOM for material A with B, C and all required components. Make BOM single level for material A. Set reorder point to material A. Run MRP MD02. It will give you planned order for A. Go to display planned order all components will be there for the planned order. Now convert planned order to Pur. req -- Pur. Order- all components will be there for the pur. order A.

I think this will solve your problem. Revert back if you have any issue.

Thanks,

Biplob

Former Member
0 Kudos

will try this!thanks.

Message was edited by: Thimmayya Belliappa