on 06-28-2013 1:04 PM
Can any one tell me how to create a Sub-Phase under a Phase in cProjects. Currently we have below
Project Header
Phase1
Task
Check list.
Phase2
Task
Check list.
User is looking for
Project Header
Phase-1
Phase -1A
Task
Check list.
Phase-2
Phase -2A
Task
Check list.
Any guidance would be great. Can it be done if so how ?
Hi Raj,
as Clara said, the sub-phase is not available in PPM project.
Beside the sub-task, you can check the scenario subproject or the programs can fit your requirement.
If the hiearchy information (Parent -Children) is not mandatory, you can also call the first-level task as 'sub-phase'. It is from dates-aspect no problem to bring the task-dates within the phase time-frame.
Kind regards
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Raj,
As far as i know the "sub phase" doesn't exist in cProjects.
You can change phases by tasks and tasks by subtasks
Project header
Phase 1
Task 1A
Subtask1A1
Checklist
Phase 2
.....
Not sure if this helps you...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.