ECC Purchase Req to SRM shopping cart conversion

satish_more3
Explorer
0 Kudos

Hi Friends,

I'm trying to transfer ECC MRP direct material Purchase requisitions to SRM to create shopping cart.

We have SRM 7.01 Classic scenario and I got to know from SAP that PR-->SC is possible.

I did all required configurations in SRM and ECC, In ECC I''m using program BBP_EXTREQ_TRANS, is it picking PReqs , but I see error in SMQ1 as "Exception condition "OBJECT_ID_NOT_FOUND" raised" with Function Module BBP_BC_EXTREQ_INB

There is dump getting created in SRM too. I'm not sure if any of the config / mapping is missing.

Please suggest on how to check/proceed to do analyze.

Thanks,

Satish

Accepted Solutions (0)

Answers (1)

Answers (1)

ricardo_cavedini
Active Contributor
0 Kudos

Hello,


Check information available in note 1646982.

Maybe it helps.

Regards,

Ricardo

satish_more3
Explorer
0 Kudos

Hi Recardo,

Thanks for reply, I have exact setup as mentioned in the note 1646982.

But when I try to transfer, I see error Exception condition "OBJECT_ID_NOT_FOUND" raised.

It seems some setup issue for sure, but not sure.

Thanks,

Satish