Dear Sir,
I want to build a Z report, through which i can get the details (Component list, qty and values) Planned and Actuall cost of Goods issue for production as we seen in production order cost analysis---cost trend.
Actual material issue cost details i got from from AUFM and S027 table but I am not getting source where i could get the details of planned material cost (planned goods issue) that could match with order planed cost. .I checked RESB table and S027 table but its not matching for all cases.
Can anybody tell exact way to get details of palned cost (component, qty, price or value) which can match order plan cost.
Regards,
Mayura.
Hi,
Before you proceed with z developments please check if these std reports are of any help to you.
S_ALR_87013099 - Order vs. Order Plan/Actual Comparison (maintain only one order if required)
S_ALR_87012993 - Orders: Actual/Plan/Variance
S_ALR_87013012 - Orders: Actual/Plan/Consumption
In case of z development.
execute program RKACSHOW (in SE38)
maintain the object number relevant to order and execute.
you will get list of tables which are relevant for cost analysis.
you may require to check each table relevant for your report development.
Please check and let me know.
Pavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.