Hi

I do maintain a supersession chain in APO.  Product A replaced by Product B and Product B replaced by product C.

My requirement in R3 ECC, is,,,, if any sales order created on A or B, sales order to be created only on C,

Plese help how this is possible,

thanks,

Regards

SRS Kannan

<personal detail removed>

Message was edited by Moderator.

1. Don't post discussion or it subject line in all CAPS.

2. Sharing personal details like mobile number, email, etc. on SCN post are not allowed.

Please review SCN Rule of Engagement and adhere them.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

if in ECC you want to replace material A & B to C . then maintain both condition record in VB11.

as Mat A replace by mat C and same for Mat B replace by mat C.

Regards

Pitabash

former_member205178
Contributor
0 Kudos

Hi Pitabash,

The Transaction Code VB11 refers to Material Determination. Thanks for giving the Transaction Code.

Thanks.

former_member205178
Contributor
0 Kudos

Hi,

Without going into any details of the interface / integration of APO and ECC, what I can say is that you use the feature of Material Determination. The purpose of Material Determination feature is to address the requirement you mentioned.

Tell me if you need more inputs.