Hi SCM Gurus,

I am new to APO and here is a very simple issue I am facing:

The value of Forecast Key Figure in DP planning book and SNP planning book has a very minor differnce, eg. its 102697 litres in DP PB and its 102690 Litres in SNP PB for a particular week. I know it is due to rounding off, but my query is that -

if the same forecast value is moved from DP to SNP why/where should there be a difference. Is there a way/place in the system to show this differnce, so that I can know where exactly this difference is coming from even if it is from rounding off.