Budget commitment on PR approval

atif_farooq
Active Contributor
0 Kudos

Hi:

We are facing an issue on budget commitment in PR. Client wants that budget on PR should get committed only when it is approved by some authority as per release strategy. At the moment budget gets committed as soon a user raise a PR which is not desirable. Please guide me if there is any standard way of doing so.

Regards

1 REPLY 1

iklovski
Active Contributor
0 Kudos

Hi Atif,

I'm afraid not. Imagine, that everyone will be able to raise PRs and, only upon the approval, people would discover that they don't have enough budget.

Regards,


Eli