on 06-24-2013 5:08 PM
Hello Everybody
CTM is generating SNP requisitions (Distribution Demand Planned KF on Plant) starting on a Sunday available on Monday. We use a 5 day calendar where Sunday is Holiday. Please suggest.
Regards
Rachel
Hi Rachel
You need to do two things.
1. Maintain shipping and receiving calendars at both locations
2. CTM will ignore these calendars unless you populate both the goods receipt and goods issue processing times in both locations with at least 1 day. The good-receipt is maintained in R/3 and updates APO via the CIF. The good issue time has to be maintained directly in APO. I agree that that being forced to do this may seem mad but this is how it works.
Best wishes
Chris
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rachel,
In CTM, you will have to use the shipping calendar and GI/GR time to make sure that it doesn't plan supply on non-working days.
Unlike ECC, in APO material you can set the GI/GR time to as low as 0.01 days which is less than 15 mins and shouldn't impact planning.
You can run a MASS job to set the GI/GR time in APO since you won't be able to enter 0.01 days in ECC..
Mitesh
Hi Rachel
No, I don't think there is an alternative but to use GI/GR times. We certainly didn't really want to use GI time at all, and GR time not much, so this was very inconvenient for us. I had a SAPNote that explained that it was necessary for these times to be maintained for the calendars to work but I cannot find it now. I took a lot of convincing by a SAP consultant that it was really necessary!
It's a long time ago now but I think we discovered that when we used GI times of less than one day (with a daily bucket size), it was rounded up to a day by the planning. The GR time in SCM comes from the GR Processing Time in the material master in ECC6, where is is maintained in days anyway.
Chris
Hi Rachel
The SAPNote is 855229. FAQ's for CTM. The relevant passage is:
Question:
Why stock transfer orders are created during shipping calendar's non working days?
Answer:
In order to consider the shipping calendar of the issuing plant of a stock transport purchase order, a goods issue time in the product view has to be maintained. The same behaviour applies for the receiving calendar and the GR time. See note 619478.
Regards
Chris
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.