hi

in msdp_admin i find my planing area glowing in red ....what is the basic minimum criteria for it to glow in green...would be nice to have your perception

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Rahul,

Put your cursor on the red ball and just hover for a second.

Best Regards,

DB49

former_member205751
Participant
0 Kudos

yup db....hav activated the planning area from ABAP editor se38 /SAPAPO/TS_PAREA_INITIALIZE  over buoyed ....at times  i jump impulsively into SDN without checking out ....i regert that ...anyways its all in the game...now my planning area is glowing GREEN..very bright indeed...

Answers (2)

Answers (2)

aparna_ranganathan
Active Contributor
0 Kudos

The planning area has to be initialized. Right click on the planning area from /n/sapapo/msdp_admin screen and choose create time series or initalize planning area option

Thanks

Aparna

Former Member
0 Kudos

Hi rahul,

Do u created CVC's in ur MPOS, once it is done then go to

planning area....> display.....> create the time series, save and activate the planning area. then the planning area will be in green mode.

Thanks

jay