Hi experts,

When I copy a network in the project builder and when the activities have constraint dates, the constraint dates get lost. In the copied network the activities will have no constraint-dates.

Is there a way to keep the activity constraint-dates during network copying?

Are there maybe different ways of copying in CJ20N a network? I dragged the network onto the worklist and dragged it then from there back onto a WBS element in order to copy it.

Thanks,

GM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Sorry, this is standard SAP behavior.  Constraints are not copied when copying a network.  Changing this behavior would require a core modification.

0 Kudos

Hi,

Thanks for your feedback.

Is it instead of a modification maybe possible to copy the constraint-dates via a development? I can see that in FM CO_BO_OPR_SEQ_COPY is an enhancement point. Did somebody tried already to copy here the constraint-dates?

We're considering to copy completeley planned networks which have dates already maintained. In the new network only some of the dates shall be changed manually.

Thanks,