on 06-20-2013 9:03 PM
Hi experts,
When I copy a network in the project builder and when the activities have constraint dates, the constraint dates get lost. In the copied network the activities will have no constraint-dates.
Is there a way to keep the activity constraint-dates during network copying?
Are there maybe different ways of copying in CJ20N a network? I dragged the network onto the worklist and dragged it then from there back onto a WBS element in order to copy it.
Thanks,
GM
Sorry, this is standard SAP behavior. Constraints are not copied when copying a network. Changing this behavior would require a core modification.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your feedback.
Is it instead of a modification maybe possible to copy the constraint-dates via a development? I can see that in FM CO_BO_OPR_SEQ_COPY is an enhancement point. Did somebody tried already to copy here the constraint-dates?
We're considering to copy completeley planned networks which have dates already maintained. In the new network only some of the dates shall be changed manually.
Thanks,
GM
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.