Goods issue have been done,still line items in service order open

Former Member
0 Kudos

Hi,

For SO, Goods issue have been done.But some line items in service order still shows open. please let me know where I want to change.

For example I created service order with 10 line items.After service order GI ave been done.Then in service order one line is still shows open.

Regards,

Gopal.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Gopal,

Try to do Technical and Business Completion of your Service order and then see the status of those items.

Regards

siva_vasireddy2
Active Contributor
0 Kudos

Hi,

   Have you Completed the Cycle till Billing