cProjects project id link to sales order

Former Member
0 Kudos

Without SAP CO (and any development), can a cProjects ID be linked to multiple sales order? How?

Also, without CO in scope, can effort capture and travel expense capture happen for a cProjects' project in CATS? (at the project or task level).

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi, you can do this through multi-level controlling. By creating WBS elements from cProjects 4.0, in SAP PS you can link those WBS elements to multiple sales order. You may prefer to create WBS element for each project element or you can create one WBS element for all the project elements. You may also assign an existing WBS element ( in PS) to the project elements in cProjects