Hi,

We are producing a finished product F1 on two production lines L1 and L2. This creates 2 dependant demands on semi finished S1.

Running MRP heuristic accumulates demands on S1 and creates a single combined order. We would like to have two orders for S1 planned on the same production lines matching the demand.

Any ideas on how this can be achieved? custom heuristic may be??

Thanks,

Zeeshan.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member189901
Contributor
0 Kudos

Hii Zeeshan,

Maintain Lot size as EX( lot for Lot) for Semi finished product. SO it'll create two receipt for Two dependent demands.

Regards

Debashis

dev_shetty
Active Participant
0 Kudos

Hi Zeeshan,

                              set up lot size profile for semi finished S1 in product master.

Thanks