Scheduling changeover times in non working times

Former Member
0 Kudos

PP/DS heuristics and or the PP/DS optimiser will not automatically place changeover times in non working times, however other smaller APS systems have such functionality. Has anyone come across this or have a method to use to get APO to do this? May be it should be a new development?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

you should remove setting "Break not allowed" in setup mode in PPM, it will place setup operation throught not-working time.

kind regards

Alla

Former Member
0 Kudos

Hi Alla,

Hope you are well.Thanks for the response. I understand what you mean but this is not the what i am looking for. The setting you suggest allows the set up duration to start before the non working time and end after it but not 'within' it.

I hope you are well. let me know what you are up to. My mail is Fred@virtegra.com

former_member583456
Active Participant
0 Kudos

Hi Fred,

in the strategy profile (/sapapo/cdpsc1) and in most of the sequence heuristic settings (/sapapo/cdpsc11) you will find a switch "Non-working times" which can be used to schedule activities into non working times.

Best regards

Thomas

Former Member
0 Kudos

Hi Thomas,

Thanks for your reply. Yes i am aware of this setting - this is the standard approach, however do you know of a way automatically (heuristic or optimiser) schedule the set up segment of an order into non working times whilst keeping the produce section in productive time? I know you can amend the strategy and use that in the heuristic but it will schedule all parts of the order in the non working time if it can.

Thanks