Double view in easy cost plannoing when accessing through Cproject accounting tab

Former Member
0 Kudos

We are trying to access sap ps easy cost planning byclicking on display/change easy cost planning from SAP cproject system accounting tab in project.

We are getting double layout of costing structure in screen.Could somebody advise why this is happening and provide the solution for this.

Thanks and Regards

Viaks

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member201206
Active Contributor
0 Kudos

Hi Viaks ,

the calling of ECP (EasyCostingPlanning) via clicking is realized using ITS (internet transaction service),     To do that, the PPM generate a URL for launch. Please check, if URL other object type get the same problem or not (you can create object link with other object type) . If opening other object works fine, please check, if there is any suspicious of generated URL.

Kind regards

Zhenbo

former_member209919
Active Contributor
0 Kudos

Hello Vikas,

Could you check in your ECC systems settings in this transaction FINR3_CPROJECTS_CUST?

Regards,

Former Member
0 Kudos

Hello Clara,

Thanks for ur reply,I have checked the setting in above mentioed tranction in ECC system.Here costing variant is assigned to controlling scenario and controlling area.Kindly advise for the next step.

Thanks and Regards

Vikas