on 06-12-2013 12:43 PM
Hi All,
When I try to release a forecast from DP to SNP with /SAPAPO/RTSOUTPUT_FCST, it seems to work perfectly for the Period Split profile I enter.
But, when I maintain a Planning calendar in the Location, the release doesn't split the forecast in line with the period split profile.
My Period split profile considers all 7 days of a week as a working day and divides the forecast among all the seven days. The calendar also considers all 7 days as working days. I am unable to understand why it works when the planning calendar is removed from the location.
Any inputs much appreciated.
Thanks,
Tabraiz.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
period split generally has nothing to do with planning calendars .
check for any enhancement used ,also check for period split setting in SNP2 tab page of product master .
thanks & regards ,
Chan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.