Hi Guys,
I have created a master recipe in ECC and trying CIF it APO. I have created new material,location, resource and cif it to APO. All get moved to APO without any issue.But when i am trying to cif master recipe, its not moving to APO. There is no error in error log.
My MR contains only one phase and one operation, and i tries cif it as both PPM and PDS.
I checked the below things:
1. Active integration model for product, resource, bom, PPM - all exists as active
2. Machine time in MR(Master recipe) - maintained.
3. Validity of MR - OK
Can u please whether any config setting is missing or any master to be checked.
Please find the screen shot for ur reference:
Please help to resolve this issue.
regards
Kishor
Hi Kishor,
Can you try transferring using CURTO_CREATE?
It might give some error / warning message which will be useful to decipher the system behaviour
Thanks,
Rajesh Manoharan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Re-create the integration model for recipe and then reactivate. Look for logs before and after CIFing recipe. If there is some error it will show up.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.