on 06-06-2013 12:35 PM
Hi experts!
I'm on a client and did the following needs: There is a project that should be done within four months, and within that period there are stages that must be met within a specified period.
eg:
- Send request within 15 days
- Issue technical opinion within 5 days
- Issuing quotes in 15 days
- Issuing purchase order in 10 days
Approaching the deadline of each item we think the possibility of activating the workflow to notify the responsible X there pending to be tratatadas.
Exists within the module PS or PP something that can be worked out for this purpose?
Unfortunately do not know anyone that module to ask a help, so if anyone can at least guide me, it'll be of great help!
Thank you and sorry for my english. It isn't very good!
suggest you to use milestone functionality in PS, Create activities in the project and assign the milestones. Once the activity is released, respective person will be notified via work flow triggered from milestones. If you are doing project scheduling then use constraints functionality to know the critical activities in the project in given dates.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.