on 06-06-2013 12:20 PM
Dear Experts,
We have created production order against WBS element for X material through MRP here we are getting problem like planned cost for the production order is not coming properly in PS
Example:
Planned cost in production order is 1000
Raw material R1 - 700
Labour cost - 300
But in PS report (s_alr_87013532) is only coming Labour cost 300 and Raw Material cost 700 is not coming.
Please provide your experts suggestion on the same.
Regards,
Naga.
If you checked opsv setting found ok as suggested, then check material master so that material is valuated or non valuated,
it's statndard/moving price have 0 value or some figure check with your MM Consultant?
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check OPSV Setting for Order type-30
make sure both are ticked.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check whether the material cost element are assigned in the value categories txn opi2.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.