1. In the report S_ALR_87013558 the actual cost is not rolling up to higher levels.
4 Upon analysis I could see that in all hierarchy reports I find the same value $ 26,075 ( checked in the table RPSCO )
5. The actual cost of level 3 is 67,968 but the level 2 actual cost of its superior wbs 20,619. Why is the level 3 cost not added to level 2 in this case ?
Q) Why is the correction posting ( CORR ) and( KOAR ) has happened in level 3 and the cost not rolled up to level 2 wbs insted reduced with KOAR
Object Actual
PRJ 26,075
WBS Level 2 20,619
WBS Level 3 67,968
Could some please explian this scenario. Thanks
Hi,
As per Sanjeev, this is due to some database incosistency only , So try for CJEN and CJBN , along with RKACOR04 progarmme for the the adjustment between Line Items and total records.
Regards,
vrkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
May be this is due to some data consistency in system, check report after reconstruction of project data base via CJEN and check PRHI table for hierarchy of wbs.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.