cancel
Showing results for 
Search instead for 
Did you mean: 

Costs not adding up from level 3 to level2 & 1 in Hierarchy Reports

Former Member
0 Kudos

1.   In the report S_ALR_87013558  the actual cost  is not rolling up to higher levels.

4    Upon analysis I could see that in all hierarchy reports I find the same value $ 26,075 ( checked in the table RPSCO )

5.   The actual cost of  level 3  is 67,968 but the level 2 actual cost of its superior wbs 20,619.  Why is the level 3 cost not added to level 2 in this case ?

Q) Why is the correction posting ( CORR ) and( KOAR ) has happened in level 3 and the cost not rolled up to level 2 wbs insted reduced with KOAR

           Object                  Actual

      PRJ                         26,075
     WBS Level 2            20,619
     WBS  Level 3            67,968

Could some please explian this scenario. Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As per Sanjeev, this is due to some database incosistency only , So try for CJEN and CJBN , along with RKACOR04  progarmme for the the adjustment between Line Items and total records.

Regards,

vrkumar

sanjeevc
Active Contributor
0 Kudos

May be this is due to some data consistency in system, check report after reconstruction of project data base via CJEN and check PRHI table for hierarchy of wbs.

Regards,
Sanjeev