on 06-04-2013 2:19 PM
Hi experts,
We are trying to configure a ChaRM action condition based on a project type.
For example, if project is a maintenance project, a configured action will appear in the Actions dropdown of a change document. Then if a project is an implementation project, the action should not appear. Is this possible? Thanks!
Luigi
Hey,
correct me if I am wrong, but I don't think there is a standard way to do that.
I would configure the action with a customer programmed schedule condition, which you can implement with the BADI "EVAL_SCHEDCOND_PPF"
Here is a pretty good example for a PPF action scheduled via BAdI:
Greetings
Christian