I understand Production Calendar for reporting.

There is one Production Calendar for one site.

How do you manage several work centers, each with own shift plans?

Thank you.

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Monika,

The Production Calendar is used to group production activity and non-conformances into shifts and dates for analysis and comparison.  The production activity is stored as raw data in several tables like ProductionLog and NCData. The tables do not contain specific shift and/or production date for the activity.  Instead, they contain an exact time stamp for when the activity took place.  This time stamp is used to determine what shift and what production date the activity took place on.  The standard reports will summarize the production on the shift and production.

Thereby I think it is not possible since there is one Production Calendar for one Site as you mentioned above.

Regards,

Alex.

Former Member
0 Kudos

Hello Alex,

thanks for your reply. We will look for a solution within these possibilities.