Availability check with MRP area at Sloc level

Former Member
0 Kudos

HI We have MRP area at storage location level maintained for materials. Stock exists in the plant in the storage location which is part of the MRP area.

Now when I create STO and try to create delivery for the same, system is giving message 0 stock available and not creating delivery. Material has 02 Avl Chck group.If I deactivate the MRP area in the material master, it allows creation of delivery.

How can I ensure that system creates delivery even though stocks exist in MRP area relevant sloc only in the plant?

Sriram

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I am sure you have already moved on from this issue, but what you mention is a limitation prior to ECC 6. You can not identify on the purchasing document the source sloc of the supplying plant. This is why you can not create the STO between sloc MRP areas. I was told this was resolved in ECC 6.

Jon