Hello Everyone !!
Here is requirement when i m doing Technical tendering & planning for project i have to show my demobilize Manpower (Labor skill & unskilled ) , Equipment etc . IS there any way available in PS (Work center , capacity planning , workforce planning ) so i can get my demobilize capacity without any development & also restrict me for assign any equipment or manpower to project if they are already assigned.
Thanks & Regards,
Yogesh Acharya
Hi Yogesh,
1) Using Workforce planning functions in PS (i.e. using "Person Assignment" tab on the Network Activity with CMP2 & CMP3 transactions) you can achieve what you are looking for to a certain extent.
2) If your capacity & workforce planning requirements are extensive then you can think of an SAP Add-on called MRS (Multiresource Scheduling). It has 'deeper functionalities' and also has more 'graphical views'. But it is not a free add-on.
Regards,
Bhushan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.