Hello experts

I am at a site using Former Budgeting, without budget structure.

Can anyone tell me the tables that can show the actual budget address of assigned budget?

This is the data in report FMRP_RFFMAV01X (subordinate account assignment not ticked).

Thanks very much!

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

For Former budget, the relevant tables would be BPJ*. Here is also a general tip to check the tables behind the report. Start a separate session with transaction ST05 and 'Activate' the trace their. The, in another session, run your report. Go back to 'ST05' session, stop the trace and display it: you will see all the queries SAP was calling during report processing.


Regards,


Eli

View solution in original post

2 REPLIES 2

iklovski
Active Contributor
0 Kudos

Hi,

For Former budget, the relevant tables would be BPJ*. Here is also a general tip to check the tables behind the report. Start a separate session with transaction ST05 and 'Activate' the trace their. The, in another session, run your report. Go back to 'ST05' session, stop the trace and display it: you will see all the queries SAP was calling during report processing.


Regards,


Eli

Former Member
0 Kudos

ST05 was a great tip - thanks!