Batch job RSVBCHCK failed during the upgrade

Former Member
0 Kudos

Hello,

I am upgrading my server to ERP 6 EHP6.
Source version is SAP ECC6 with EHP4 SP11. Upgrading to EHP6 SP5.         
During the Preprocessing phase I am stuck in the phase                 
MAIN_INIT/JOB_RSVBCHCK2. I find the following log:-        

CHECK OF UPDATE TASK ERRORS and RETURN CODE in RSVBCHCK.EV1            
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~         
1 ETH010XRSVBCHCK: Check of open update requests                       
A2EEMCEX 151 Entries for application "03" still exist in the           
extraction queue ->                                                    
A2EEMCEX 141 Struct. appl. "03" cannot be changed due to setup         
table -> Long text" ""MC03BF0SETUP""500" 

Can anyone help?  

Regards

Suniana                          
                                                                               

Accepted Solutions (1)

Accepted Solutions (1)

anandkarthik_raja
Active Participant
0 Kudos

If you are still in uptime and there is productive operation going on then you may go ahead ignoring the error

In general this is the rule of thumb :


Make sure that you have cleaned up all outstanding updates and for
4.x and higher, all outbound queue RFC calls by the JOB_RSVBCHCK_R or
JOB_RSVBCHCK_D phase (during downtime) at the latest.

Please see 689574 -> Section: Phase JOB_RSVBCHCK2

Section: Phase JOB_RSVBCHCK2
The text should say:
"If errors occur in this phase and you are still in production
operation you can skip these errors with ignore without entering a
password.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

For now you can ignore the error during downtime when job JOB_RSVBCHCK_D fails you can follow instructions in SAP Note:1705774

Regards,

Sohrab Kapoor

Reagan
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You need to clean up the queues shown in Tx SMQ1.

Process them using the Tx LBWE - "Job Control" link in the "Update" column.

Plan a job with the start date "Immediate".

Also reorganize the incomplete update requests:

Note 67014 - Reorganizing update requests

Good Luck

RB