Hello Guru's;

I make the Status Synchronization from Project Phase to the Item DP, but doesn't work!!

I configure the follow status:

DFM4
SourceTarget Old StatusNew StatusOperation Name Op.
PDPDCP220 Initial250 CanceledDFM5Canceled
PDPDCP220 Initial350 CompleteDFM3Close
PDPDCP250 Canceled220 InitialDFM6Reset canceled
PDPDCP250 Canceled350 CompleteDFM3Close
PDPDCP350 Complete220 InitialReset complete

when I change status from Phase Any of those status  doesn't work to the Item DP.


Please, help,

Best regards.

Mariano

Accepted Solutions (1)

Accepted Solutions (1)

mariano_sabiche
Active Participant
0 Kudos

Hi,

Only Works from Decisión Point to the Project Phase status and not from Project Phase to the Item Decisión Point!!

Best regards.

Mariano

Former Member
0 Kudos

Hi Mariano.

How did you solve this. I'm struggling to get this synchronization to work from Item DP to Project Phase.

I have mapped Item DP with Project Template Phase

I have made config "Map Portfolio Management Status to DFM BUsiness Transaction" (the outbound from Portf. Mgmt.) Here I have the old and new status of the Item DP mapped to DFM3 (Complete).

I have mapped config "Map DFM BUsines Transaction to Project / Initiative Business Transaction" (The inbound to Cproj.) Here I have project phase as target with Bus Trans: DX18 (Complete phase) and Item DP bus trans: DFM3 (complete) as source.

What am I missing?

PPM 5.0 sp7.

Thanks,

Morten

mariano_sabiche
Active Participant
0 Kudos

Hi Morten;

My synchronization works wrong in some cases, I have a OSS message with SAP.

Why you mapped Ítem DP with Project Template Phase? Are you sure that it's a Template Phase?

Please share screenshot to help you.

Regards,

Mariano

Former Member
0 Kudos


Hi Mariano.

I mapped the Item DP with Template phase because my Project Management Project is created from a Project Template, but I'm not sure if this config is necessary?

The reason I mapped this was, actually, because I was thinking of how the system would know that I needed the Phase change to happen when closing the first Item DP. So I mapped the first Item DP with the Phase of the Project Template (I only have one phase).

Porft. Mgmt -> Global Customizing -> Portf. Independent Settings -> Map Item Type to Project Template or PS Project

I've added screenshots of the outbound from Portf. mgmt. and Inbound from DFM.

mariano_sabiche
Active Participant
0 Kudos

Hello Morten;

Ok. You mapped the Ítem DP to the Phase Project Template.

But this configuration doesn't mather.

I think you have ton configure this SPRO functionalities:

1) Map Project / Initiative Business Transaction to DFM Business Transaction.

2) Map DFM Business Transaction to Project / Initiative Business Transaction.

3) Map Portfolio & Project Management Status to DFM Business Transaction.

4) Map DFM Business Transaction to Portfolio Management  Status.

I think that you forgot to configure the las configuration "Map DFM Business Transaction to Portfolio Management Status"

Where do you tested?

Try to configure it.

Regards,

Mariano

Former Member
0 Kudos

Hi Mariano.

I only need the synchronization to happen from Item DP to Phase (Item leading scenario).

So do I still need to configure the no. 1 an 4 SPRO functionalities?

Regards,

Morten

mariano_sabiche
Active Participant
0 Kudos

Hello Morten;

Sorry for my late response, I returned from vacations.

The point 1 and 4 it's not necessary for Ítem DP to Project Phase.

Have you solved this issue?

Regards,

Mariano

Answers (0)