Hi Experts,

I'm new to SolMan and now I'm trying to transport to multiple client (500 and 510).

My solman is 7.1 SP 04.

The TMS configuration is like this:

400 (customizing only) --> /transport group/ to 500 and 510 --> 600 (PRD)

420 (workbench only) --> 500 (QA master) --> 600 (PRD)

I've created a project in SOLAR_PROJECT_ADMIN and assign 2 logical system:

A --> Dev 400, QA 500, Training 510, PRD 600

B --> Dev 420, QA 500, PRD 600

I've clicked 'check' in SOLAR_PROJECT_ADMIN --> System Landscape --> Change Management, All green and then create the task list (also unlock the groups).

I've set the training client as 'Target system' in SMSY --> Logical component --> system roles

When I go with the workflow ( create change request and the change document ), I managed to create TRs and release them. But when I set the action to 'to be tested', the TR from 400 only transported to 500 (QA) but not to 510 (training).

I can still continue to transport to PRD (continue the change document workflow) but I can't transport customizing object to 500 and 510 at a time.

I've also tried the use 3 logical component:

A --> Dev 400, QA 500, PRD 600

B --> Dev 420, QA 500, PRD 600

C --> Dev 400, QA 510, PRD 600 (i've tried both with PRD 600 and without)

And create new project, still can't transport to 500 and 510 at a time. I've also tried using other systems ( 510 as demo, evaluation ) but still no work.

Please advise to solve this multiple client transport using SolMan ChaRM.