Hi,

 

I have create PS project from PPM Item. WBS-elements have actual cost. I use /RPM/FICO_INT_PLANNING programm. And now I have a warning:

 

No link exists between SAP PS Project element and selected SAP PPM items

Message no. RPM_FI_INTF016

 

How to transfer WBS-element financial data (actual costs) to Initiative?

 

PPM 5.0

SAP ERP 6.0

 

Regards,

Karm

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Ensure that the WBS element(s) are object linked to the item.

Portfolio Management -> Base System Interfaces -> Application Object Settings -> Define Object Link Types

amit_maheshwari2
Contributor
0 Kudos

Hi,

Have you created the project automatically for portfolio item?

If yes, then check it should have created 2 object links for PS Project - one with 0INMPSPD (under Relationship tab) and another with 0RPMFIPROJECT (under object links tab)

The project with object link type 0RPMFIPROJECT is used for cost integration.

Hope this helps.

Cheers

Amit