on 05-27-2013 3:10 PM
Hi,
I have create PS project from PPM Item. WBS-elements have actual cost. I use /RPM/FICO_INT_PLANNING programm. And now I have a warning:
No link exists between SAP PS Project element and selected SAP PPM items
Message no. RPM_FI_INTF016
How to transfer WBS-element financial data (actual costs) to Initiative?
PPM 5.0
SAP ERP 6.0
Regards,
Karm
Ensure that the WBS element(s) are object linked to the item.
Portfolio Management -> Base System Interfaces -> Application Object Settings -> Define Object Link Types
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you created the project automatically for portfolio item?
If yes, then check it should have created 2 object links for PS Project - one with 0INMPSPD (under Relationship tab) and another with 0RPMFIPROJECT (under object links tab)
The project with object link type 0RPMFIPROJECT is used for cost integration.
Hope this helps.
Cheers
Amit