Hi All,

          Currently we are facing one issue. For one particular Vendor Alone the AB and La date are same.I just want to know if there is any User Exi or any program to find the how the delivery date is being calculated in the PO. Kindly help us in this.

With Regards,

Priya.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

The delivery date in PO is calculated based on the days mentions in Material master MRP2 tab. as planned Delivery time and GR processing time mentioned .

Regards

Pitabash

former_member186385
Active Contributor
0 Kudos

Hi,

Delivery Date in the PO will be calculated based on the PLANNED DELIVERY TIME from the MRP2 view for the respective Plan and the storage location

regards,