on 05-24-2013 2:26 PM
Dear SD Gurus,
I'm new in SAP SD module and hence seeks help from all the SD Gurus.
Also please correct me if I tried anything wrong.
The following is the scenario in STO .
Assuming my industry is furniture mfg industry.
I have two plants 1st : Manufacturing and 2nd Delivery plant
DEL Plant sends PO to MFG Plant and MFG plant in turn after production delivers to DEL Plant.
Upto here every thing is fine.
Now if DEL Plant sends PO with BOM , firstly how BOM can be exploded in PO secondy how I can link it to delivery document.
Example:
Table(main item)
Leg(sub item) 1 * 4
Tops(sub item)1 * 1.
Thank you in Advance,
Raj.
Hi,
Normal STO process does not support BOM
BOM is supported only for subcontracting PO
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.