can we do calibration process with QM only with out PM

former_member798593
Participant
0 Kudos

Hi experts

We dont have PM module , But we need to do calibration for all equipments in our plant.

Based on the due date system should trigger the calibration of the instrument

Is it possible with QM module with out involving PM and WORKFLOW.

regards

Satya

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Without PM, how you can map the equipments??

All other details such as Task List, Maintenance Plan, Maintenance Order, etc., can be mapped only through PM Module. Without that, you can't map the calibration process.

Check the document for Calibration Master Data.

http://scn.sap.com/docs/DOC-29393

former_member798593
Participant
0 Kudos

Hi Maheswaran KD

Thank u very much for your valuable effort

Regards

Satya

Answers (2)

Answers (2)

former_member42743
Active Contributor
0 Kudos

If you have QM, you have PM.  They come along for the ride as part of the logistics module.  There is not added cost.  But you do have to set up some basic config and of course the master data.

FF

former_member207800
Active Contributor
0 Kudos

As aleady mentioned, the PM module functionality is mandatory for calibration process.

In other words, the QM module functionality is optional for calibration.

Regards, DoWook KIM