on 05-22-2013 3:39 PM
Dear Guru's;
I have a request that user need see the % of all task completion in Project Management Phases and in consecuence in Project Definition too.
When I check the standard of SAP PPM 5.0, only Tasks have the % of completion, but not the phases and Project definitions.
I have this solutions to give to the users:
Please, someone has been worked with this kind of request of % of completion in Phases and Project Definition?.
Best regards.
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Zhenbo;
You mention that using the field "work complete" in Project Definition is the solution?
It's an alternative of using but i don't know if it's users want to complete this field. Maybe complete automatically is the solution (BADI).
I would create a Z field in detail and table view for phase, only for viewing.
Users want to simulate Microsoft Project with Project Management.
Thank you for your comments.
Best regards,
Mariano
Zhenbo;
I have the solution to this issue. I will créate a Task at Project Definition Level and related to the other Task at Phase level. This first task will show me the % of complete of all the task like a Project Definition, with relationship to other Task at phase level (with the % of completion of the phase). This is an enhacement with BADI ZDPR_BADI_ATRIBUTES.
What do you think?
Thank you for your answer.
Best regards.
Mariano
Hi Mariano,
yes, you can add a task under project header to represent the project regarding completion. But how would you do for the phases?
You surely create for each phase a task (under project header or under phase) accordingly. But it is somehow overhead, because you actually need an additional field, but now you have an object to get it.
Kind regards,
Zhenbo
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.