GR based IV indicator not activated on the SRM PO in backend R/3

Former Member
0 Kudos

Hello Experts,

My client is using SRM 7.0 with ECS scenario & R/3 ECC 6.0 as backend.

Vendor master is set up in back end R/3 with the GR based IV indicator active(so also ERS indicator/GR expected /IR expected as well).

These vendor masters are replicated frm R/3 to SRM server via batch jobs.Same is updated accurately in SRM supplier rercords.

The  PO is created in SRM(ECS) & replicated to backend R/3 .

Upon checking the GR based IV indicator is active in SRM PO item level(so also ERS indicator/GR expected /IR expected as well) But the SRM po replicated in back end R/3 is missing the GR based IV indicator .Checked via ME23N in R/3 at PO item level

Other indicators ->ERS indicator/GR expected /IR expected are activated ok

I tried to push PO via FM BBP_PD_PO_TRANSFER_EXEC_V2 from EB.But no impact.I also tried to replicate vendors again from R/3 to SRM.No impact

Pl can you advise what is wrong? & How to X check?

Thanks a ton!

Ranganath

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ranganath,

Reading through issue does NOT indicate that there is an issue in the interfaces between CLM <--> ECC or CLM <--> SRM.

Perhaps you have posted the message in the wrong forum. Please confirm.

Regards,

Parankush