SLR_558 report

Former Member
0 Kudos

Dear Experts,

    SLR_558 report shows budget vs actual values. If we book costs on a wbs, budget is consumed and available bdgt reduces.

Similarly, when revenues (eg. debit memo) are posted , slr report shows increase in available values coz of the formulas in the form / report.

How to avoid this .

Kindly find the attachment and suggest.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Supriya,

Check the cost elements that are being used. It may not be complete Revenue elements (CElem category -11) and may be of cost reducing revenues (CE Category -1).

Regards,

Bala

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Thanks all for your response.

Closing the issue.

Former Member
0 Kudos

Hi ,

As per the Mr. Balachandar, It was right the Revenue cost element leads to increase the available budget  for the respective WBS postings., So try to exempt the revenue cost elements from the budget process by OPTK t.code  ( Exempt Cost Element Availability Control ) .

Specify : Controlling Area, Revenue Cost Element which requires to be exepmted from budget , and Name of the cost eleement.

I hope it will resolves your requirement.

Regards,

vrkumar.

Former Member
0 Kudos

Hi Supriya,

In addition to Bala's reply, also have a look at following SAP note showing assigned value calculation.

Note 178837 - Availability control: Incorrect assigned value?

Regards

Tushar