I am in trouble about Optimizer and Order Date.(Avail/Req Date)
[What I want to do]
After executing Optimizer, Order date for in house should be middle of the Month.
# Time Bucket is Month
[Current situation and Configuration]
Currently the order date is always middle of the month. (eg. 15th June 2013)
Configuration
1.SNP Optimization Profile
Bucket Offset During Production: 0.5
Bucket Offset During Shipment: 0.5
2.Product master/ Lot Size Tab
Period Factor:0.5
#It seems this value is nothing to do with Optimizer
This is only for Heuristic.
Someone, please advice me if you know other neccesarry configuration.
Regards
Ryo
Hi,
You can also maintain bucket offset in PDS/PPM. If its maintained there then value from optimizer profile will be ignored.
I think this configuration is sufficient to create receipts in the middle of the month.
Experts, please add in if I am missing something.
NT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.