on 05-21-2013 11:26 AM
Hi Experts,
While i am doing Installment plans in FPR1 i am getting the above error
Message no. >4133)
for this error i changed system calendar from Germany to India also but i am not able to do it and more over i try to change the limit year from 2010 to 2050 for India factory calendar but system not accepting it so i expect best solutions from you all experts.
Regards,
Cherry.
You state you changed the system calendar, & extended it to 2050. Does this mean you have modified the validity period in Transaction SCAL?
Ensure the factory calendar (& holiday calendar) is extended passed the date you are attempting to process.
If thats what you have already done, I'll have a further think about it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Then you need to extend the validity period of your chosen calendar in SCAL.
Extend the associated holiday calendar, then the factory calendar.
Be aware this is a client independent change, & will require you to transport the entire calendar
Alternatively you can maintain it in the Production client (which is not recommended Note: 574628)
I suggest reviewing Notes