on 05-21-2013 10:08 AM
Dear PS experts,
It seems assigning Standard Milestone to Std netowrk is not possible. Kindly confirm that it is only possible to assign milestones in Cj20n traxn to project.
Thanks
Jatin
When you are in CN01 / CN02, choose the corresponding activity and then from Menu bar, choose Activity --> Milestone Overview. Here you can maintain the same.
Regards,
Bala.