How to Assign Standard Milestone to Std netowrk

Former Member
0 Kudos

Dear PS experts,

It seems assigning Standard Milestone to Std netowrk is not possible. Kindly confirm that it is only possible to assign milestones in Cj20n traxn to project.

Thanks

Jatin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

When you are in CN01 / CN02, choose the corresponding activity and then from Menu bar, choose Activity --> Milestone Overview. Here you can maintain the same.

Regards,

Bala.

Former Member
0 Kudos

Thank you  Bala.

Best Regards,

Jatin