All operations lie on critical path and no float time for operation after capacity leveling of network.

Former Member
0 Kudos

Hello colleges.

We have simple networks in PS.

We see the critical path for networks (operation 21, operation 22 and operation 31) and float time for operation 11 (pictire before leveling).

We see that all operations of networks lie on critical path and no float time for operation 11 after capacity leveling (pictires after leveling and after scheduling) .

Is it right? Is there possibility to see, for instance, float time for operation 11 after capacity leveling of the networks?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Check the dates screen, looks like constraints were placed on each activity.