on 05-18-2013 10:18 AM
Dear all,
we have implemented source inspection,we are facing one difficulty.In purchase order we have not given Qty schedule wise but gave a single PO with no schedule..Now issue is that sometimes party is not able to deliver full lot and we want to convert partial qty from QI07 to QA32,bacause balance qty now will be supplied later on.Pl suggest.
Thanks in advance
Vikas
This is drawback to using a Source Inspection.Partially lot creation or processing not possible.
Only way is to add line items in PO for required qty,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Vikas
Source inspection lot is not stock relevant so no need to bother about that.
regards
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.