Hi,

A macro is created. When it is executed at aggregate level it is working fine. But at 'detailed level' it is not working.

I tried with following two options -

1. Setting the level in the macro definition and executed the macro in interactive planning.

2. Defined background job with aggregation feature and run the job.

But in both the cases it is not working.

Please let me know if further information is required.

Regards,

RS

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello YR,

Can you try using the Collective macro where 1st macro performs the drill down and the other one performs the calculation.

This should solve your issue.

Regards,