PPM 5.0 Fileds Sync to cProjects

Former Member
0 Kudos

All i am trying to sync PPM5.0 fileds to cPorjects.  I have below config in place ( "Maintain Attributes for Syncronization" through DFM) and Project Name is being Synced when i create or udpate an Item.

I am planning to Sync other fields like Dates, Description and other fields. When i try to configure "Maitain Field Mapping" under DFM settings i dont see Main Group as "PPO\Item". 

All i am trying to do is Sync PPM item to cPorjects. Is there any config i am missing ?

Any help would be greatly appreciated.

Accepted Solutions (1)

Accepted Solutions (1)

former_member209919
Active Contributor
0 Kudos

Hello,

You have to review these settings :

1. Maintain attributes for sync scenario

2. Maintain object sync structures for Object grouping -->  Check here you have defined the item structure In and Out.

Regards,

Clara