Hello ,

As the client want to have a delivery plan for the materials that they sell by SD, was my idea to create a delivery plan in PS SAP.

IS this possible ? Can we deliver a material in different deliveries ?

Is there a possibility that delivery dates can be changed en mass y triggering certain milestones or changing these milestones ?

Thank you

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

At the component overview screen, you can specify the required delivery date for each component.

That would be your planned delivery date for each component and can be seen report CN52N.

Coming to the project deliveries, on the project delivery screen system will bring up all the materials available in inventory. now select those items and delete them and save so system creates delivery for the items which are being remain on the delivery screen.

by doing this process you can have multiple project deliveries.

Thanks,

Sudhakar

Message was edited by: Sudhakar Pappu