Hello APO experts,
There is business requirement to make a singe purchase order during SNP deployment run by combining multiple Preqs within given period. For example if we are running SNP deployment weekly for 7 day deployment horizon it should combine all 7 days pres and create one single PO instead of creating multiple POs.
Thanks in advance for your input on this.
Raj
Hi Raj,
Try running deployment in WEEKLY planning bucket, this might solve your purrpose.
Thanks
Yogesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try creating a deployment profile with user created fair share rule. Run deployment and see if it works.
NT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii raj,
Creation Of PO totally depends on On the TLB Profile. Where you can set TLB parameters.
go through the SAP help on Tlb Profile.
http://help.sap.com/saphelp_ewm70/helpdata/en/76/2f7b37e12a7a09e10000009b38f889/content.htm
On the basis of these parameters , system will club desired Deployed Purreqs and will create one PO.
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.