on 05-12-2013 9:28 AM
Dear Exparts,
We have a LPG material, code: 4000000000. This material Group is Finish Goods, Material General Item Catagory is Standard. At a time we can create sales order by multi users for this material. But during Delivery & PGI if we want use this material at a time by multi users then one delivery document get Order qty but others Delivery document qty show null. How can we use at a time same material by multi users in SD Delivery Level?
thanks
Md. Enayet Hossain
Hi Enayet,
As already suggested by Mohamed Naseem, please have the late lock option.Before doing this consider the implications as mentioned by Mohamed.
Other possible option is, create background jobs for Delivery and PGI.
Regards, Sai Krishna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Enayet,
Please Try Material Late Lock option and this will help you to Process Goods Movement for multiple users at a time for same Material. Please Refer T.code OMJI . But this is client level so activate for all Materials and this may lead to performance issue..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.