on 05-10-2013 10:49 AM
Hi All
In Recipe development, we have custom Specification type (R&D) as Primary Output specification. All the ingredients used in Recipe are of Specification type REAL_SUB
Due to our business process we do not want to assign material to Specification type R&D. so this is creating hard stop while doing the Synchronization to BOM.
Our question is how we can replace the Specification of type R&D in Recipe development with Specification type REAL_SUB at the Synchronization to BOM option.
Our main objective is to restrict the Recipe only to R&D team until the Recipe is approved and corresponding Material master is created.
Many thanks in advance
Yasar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yasar,
If the main objective is to restrict the recipe only to R&D team till approval, it can be achieved using statuses and authorizations. Before approval, you can have an intermediate status to indicate that a material master has been created and linked to the specification.
Best regards,
Rajeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.