on 05-09-2013 2:37 AM
When the activity dates in the Project (CJ20N) is not in the current year, the purchase requisition is getting created with 0 gross price (price is not getting picked from the outline agreement). This gives scope for creating PR without approvals. Is there any pointers to ensure system does not allow to create PR (from CJ20N) with zero gross price ?
If i right assume your query then Execute OIPSMDMAT t-code and do mandatory price/currency (RESBD-GPREIS) field so that user could not save PR with zero price.and talk to MM consultant for the same.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Besides Amaresh suggestion, check the validity date of schedule agreement date.
Is activity dates are lying within project definition or not. try to adjust the activity dates into future and then create PR.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The activity end date was set to past date and system assuming that there will not be planning activities being performed. To pick the data from other sources it is required to have your activity in active status (I did not mean your activity has been completed though still having REL status).
So please maintain the finish date to the future date.
Thanks,
Sudhakar
Hello Sankaralingam,
You can make use of combination of "user statuses" and authorization objects, to control this.
Only person authorized to a particular user status (which allows creation PR) will be able to create it.
You can do this configuration in OK02
Hope it helps you.
Best Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amaresh,
We do not want any user to create PR with zero gross price. We are thinking of doing an enhancement for the system to throw error message to stop the user if user enters any dates other than current year. Attaching screenshots for better understanding. Trying to find if there is any other better way to achieve the goal.
Note: When the dates are set in current year (2013), then the PR picks the price from the contract. This is the ideal situation.
Thanks,
Sankar
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.