TO and FROM date from SRM to ECC for Service PO

Former Member
0 Kudos

Hi friends

In outstanding confirmation report we want to and from date fields of a service po, when I checked in ECC I did not find them in ME23N.So any one help me out where to pull the data from to get this data.

Thanks & Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

robin_janke
Contributor
0 Kudos

Hi,

this data is in ECC in table EKKO: validity start and validity end.

The 2 fields are hidden in the standard delivery of the screen display of ME23N, this can be changed in customising.

Regards,

Robin

Former Member
0 Kudos

Hi Robin,

Thanks a lot for your answer.

Former Member
0 Kudos

Hi Robin,

This is  giving  for header level dates if we have 2 line items with different to and from dates in a PO.Then it will give a range for both line items in my report but I want a report where the PO of service for 2 line items have different dates,when I keep those dates in SRM.Please help me for this type of situation.

Thanks & regards

Former Member
0 Kudos

Hello - can you please tell me if you ever got an answer to your question? We have the same issue where we need the to and from dates at the line item level.

Thanks!