Hello Gurus,

We ran PPM Imod job in R3 few days back, to CIF PPM to APO. This has overwritten manual PPM changes done by user directly in APO.

Now we need to revert older PPM values in APO.

DO we have any method which will revert "APO CIF changes" and bring back older data.

Any other way to restore older PPMs ?

Thanks in advance...

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Pratiksha,

Unfortunately there is no way to restore manually entered data in PPM's after transfer.  You can go back to an earlier version of the PPM by transferring an earlier PPM integration model (if you kept any).

If you have a record of the changed data in a spreadsheet or text format, you may be able to use MASSD or the FUNCTION_LOADER_INLAY program in APO to update the PPM to your requirements.